Who this checklist is for

I'm not an engineer. I'm an office administrator who handles purchasing for a manufacturing floor — filters, belts, consumables, and every so often a piece of capital equipment. When our old compressed air dryer started failing in 2024, running the replacement purchase landed on me.

Since then, five different people have asked me the same question: how does an admin buyer source an industrial compressed air dryer without pretending to understand compressed air systems?

Here's the checklist I wrote down afterward. Seven steps, arranged in the order I got them wrong the first time — not the order that would look neatest.

Step 1: Get the requirement on paper, with the operating conditions on it

Your maintenance lead probably knows exactly what's needed. The problem is that knowledge lives in his head. Before you send the first RFQ, get it in writing, even if it's three sentences in an email: rated flow (scfm or Nm³/h), working pressure (barg or psig), required pressure dewpoint, electrical supply, ambient conditions at the install point (heated room, unheated, high summer humidity, outdoor enclosure), and which section of piping this thing ties into.

Why so specific? Because dryer capacity ratings aren't fixed numbers. A dryer rated at a given scfm is rated at a specific inlet temperature and pressure. Change the inlet conditions and the effective capacity moves — sometimes a lot. A dryer that looks generous on the datasheet can end up undersized for your actual plant.

If the request comes in as "same as the one we have," push back gently. Five minutes of questions here saves a week of re-quoting.

Step 2: Don't let the vendor make the type decision for you

Here's the short version of the four dryer types you'll be quoted on, which is roughly as far as a non-engineer needs to go:

  • Refrigerated (cycling or non-cycling) — pressure dewpoint around +3°C / 38°F. Adequate for most general plant air where lines aren't exposed to freezing conditions.
  • Desiccant, heatless — pressure dewpoint down to −40°C / −40°F and sometimes lower. Uses a portion of the dried compressed air as purge to regenerate the desiccant bed.
  • Desiccant, heated — similar dewpoints, less purge air, but a heater adds electrical load.
  • Membrane — small flows, moderate dewpoint reduction, simple installation, some sweep-air loss.

I'm not an engineer, so I don't make the type call. What I can do is make sure the person who does make it has the right inputs and that the quote I receive reflects that decision in writing.

One question most buyers skip: ask whether the dewpoint requirement comes from the process or from habit. If the answer is "we've always done it this way," ask the process engineer what actually breaks if the dewpoint loosens up. Sometimes it matters a lot. Sometimes it's a leftover number from a machine that was replaced in 2011.

Step 3: Ask about purge air and regeneration cost before anything else

This is the step that quietly separates a good decision from an expensive one, and it's the one I nearly missed.

Heatless desiccant compressed air dryers regenerate by bleeding off a share of already-dried air. That air was compressed by a compressor that draws real power. So a dryer with a low purchase price and a high purge rate can cost more to run than a dryer that looked more expensive at the quote stage.

I'm not going to give you a purge percentage, because it varies by model, cycling strategy, and inlet conditions, and I'd be repeating marketing numbers. Ask for it in writing instead: what share of rated flow goes to purge at our operating conditions? Put that number on the comparison sheet next to the purchase price.

Step 4: Ask "what's not included" before you ask "what's the price"

This is where I've been burned, so I'll tell it plainly.

I once placed an order with a new supplier whose quote came in about 15% under our regular vendor. The PDF looked professional. Equipment arrived on schedule.

Then the invoices started arriving. Freight, which we'd assumed was included. A rigging and setting allowance. A small charge for pipe adapters that weren't part of the package. Individually none of it was dramatic; together it erased the savings and added a month of back-and-forth with finance over what the purchase order actually covered.

Now my first question on any quote is: what is not in this number, and under what conditions would those items get billed? Freight, rigging, startup and commissioning, filtration, drain treatment, demo and disposal of the old unit, electrical connections, and extended lead-time surcharges are the usual suspects.

A quote that lists those line items up front and totals to more than a competitor's headline number is usually the cheaper quote in the end. Not always. Usually.

Step 5: Trace the performance claim to a standard, not a brochure

Compressed air quality is graded under ISO 8573-1, which defines purity classes for particles, water, and oil. The water classes are expressed as pressure dewpoint: Class 1 at −70°C, Class 2 at −40°C, Class 3 at −20°C, Class 4 at +3°C, and so on. So when a supplier says their unit delivers "ISO Class 2 air," that claim has a defined meaning — and you can ask what testing supports it.

Two other names worth knowing: ISO 7183 covers compressed air dryer specifications and performance testing. CAGI (the Compressed Air and Gas Institute) publishes validated performance data for member companies, which is useful for checking whether a quoted flow rating was measured under a consistent method or picked from the most favorable corner of a test matrix.

These standards were current as of 2025. Standards get revised, so verify against the latest published version before you lock a spec into a purchase order — and if you're not sure what revision applies, that's a question for your engineering contact, not for me.

Step 6: Compare total cost over the service life, not the capital number

At some point you'll be staring at two quotes where one is meaningfully cheaper up front and your instinct is to take it. Run the arithmetic on a five-to-ten year horizon before you do.

The pieces that belong in the comparison: purchase price, installation and commissioning, annual energy draw, purge air cost (Step 3), regeneration heat if applicable, replacement filter elements and desiccant, drain valve maintenance, and the labor cost of whatever preventive maintenance schedule the OEM requires to keep the warranty valid.

When I ran this on our 2024 replacement, the cheaper unit's running cost advantage disappeared by year four. That's not a universal result — it depends entirely on your duty cycle and energy rate. But you can't know which way it lands without doing the arithmetic.

Step 7: Pin down service, spares, and warranty in the order

The last step is the least glamorous and the one most likely to cause a headache in year two.

Before signing, get written answers to: service response time and who actually performs it (the supplier's own technicians or a third party), spare parts availability and typical lead time for filter elements and desiccant, what voids the warranty (usually missed maintenance intervals, unauthorized service, or operation outside rated conditions), and whether startup and commissioning by a qualified technician is included or billed separately. If startup by a technician is a warranty condition, it needs to be on the purchase order, not arranged informally afterward.

Three mistakes I've made or watched others make

Comparing quotes with different ambient assumptions. Two suppliers quoting "the same" dryer can be rating it at different inlet temperatures. The lower-priced one may simply be quoting a smaller unit.

Assuming freight is always included. It isn't, and it isn't always obvious from the quote layout either.

Buying on the capital number and defending it to finance with a spreadsheet built afterward. If you build the total-cost model first, you usually get a defensible answer. If you build it after, you get a rationalization.

The whole checklist takes maybe two hours spread across a couple of weeks. The alternative — re-quoting, re-explaining, and eating a surprise invoice — takes longer.